Project Budget
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Project Phase | Total Cost | |
|---|---|---|
| Acquisition (1998 & 2000) | ||
| Woodward and Annex Buildings | $400,000.00 | |
| Phase 1 | Complete | |
| New Roof | $218,941.42 | |
| Phase 2 | Complete | |
| First Floor Retail & Building Stabilization | $542,512.41 | |
| Phase 3-1 | Complete | |
| Abatement Asbestos + Lead Based Paint + Repointing |
$956,472.85 | |
| Phase 3-2 | Complete | |
| Abatement - Restore Windows | $402,300.60 | |
| Total Work Completed to Date (including Acquisition) |
$2,520,227.28 | |
| Phase 4 - Theater will be operational when done. | ||
| Theater & New Rear Annex | $6,214,914.41 | |
| Equipment | $484,120.00 | |
| Phase 5 | ||
| Complete Primary Annex Interior Work | $1,924,930.04 | |
| Equipment | $535,000.00 | |
| Phase 6 | ||
| Restore - Rehabilitate Opera House 2nd Story & All Storefronts |
$954,359.60 | |
| Phase 7 | ||
| Complete Secondary Annex Interior Work | $743,322.12 | |
| Phase 8 | ||
| Create Basement Retail/Arts Spaces + Exterior Areaways |
$813,499.18 | |
| TOTAL PROJECT COST | $14,190,372.63 | |